Reaching new heights

A month into 2017 and we’re reaching new heights on our home office project.

The most visible progress on our site has been the stairway and elevator cores for the building, which are now standing five storeys tall. The project team has also been busy pouring the concrete foundation, placing the steel building columns and developing the floor structure.

It's been nearly a year since we gathered the community to unveil the plans for our new office – and we have enjoyed keeping our neighbours informed of our progress ever since. Just before the end of the year, we held our third information session at the Admiral Beatty and we look forward to continuing to engage with the community in the coming months.

Looking further ahead in 2017, the full height of the steel will be completed by late spring / early summer and the installation of the stone facade on the exterior will soon follow.

Take a look at our gallery of recent photos.